2025-26 Construction Schedule
Brighton Construction Schedule
Brighton Construction Schedule for March 16-27
Below is the anticipated schedule of work from March 16 to 27, 2026.
Brighton High School
Technology Suite:
- Shop equipment connections and adjustments
- Electrical finishes
Door 20 Addition:
- Door installation upon material availability
Music Suite:
- Electrical disconnections and rough-in
- Mechanical rough-in
- Framing
- Panel work
Athletic Fields and New Entry Lane:
- Subject to material arrival, there will be placement and installation of stone for new entry lane, drop-off loop and temporary laydown area which is next to the Buildings and Grounds Lot
- Site prep including soil stockpiling and drainage work
Boiler Room/Main Distribution Panel:
- Mechanical and plumbing rough-in
- Cooling tower rough-in – Welding and roof work
- Electrical conduit rough-in and panel work and transformer install
- Plumbing sump pump piping
Twelve Corners Middle School
STEAM Suite:
- No work during this time
Stairwells:
- Painting
- Ceiling work
Elevator:
- Electrical card reader programming
- Electrical panel work and testing
French Road Elementary School
Exterior Canopy:
- Roofing work dependent on weather
Main Lobby/Secure Vestibule:
- Metal coiling door electrical connections
- Door hardware
- Painting touch-ups
Please note that our schedules are always subject to change based on many factors and opportunities including manpower, material availability, and weather.
Brighton Central School District construction projects will follow the local Town of Brighton Construction Noise Ordinance Hours of 7 a.m. to 7 p.m. Monday through Friday. Please anticipate that there may be varying loud noise between those hours to allow for construction to advance.