Construction Schedule
Brighton Construction Schedule
Brighton Construction Schedule November 16 to 27, 2026
Below is the anticipated schedule of work from November 16 to November 27.
Brighton High School
Music Suite:
- Punchlist work consisting of door adjustments, drywall work, lighting controls
Hallways:
- Painting
- Flooring Prep including grinding and moisture mitigation
- Annunciator Panel Work
Rooms 154/156/Main Lobby/352/354/408:
- Electrical Rough-In
- Foundation Work – Sampling Crusher for Proctor/Compaction
- Framing
Athletic Fields and New Entry Lane:
- Soil testing around the site for topsoil analysis – following DEC guidelines
- Underground Drainage Work – following DEC guidelines
- Saw cutting asphalt & Excavation
- Conduit Install & Light Pole Base Rough-In
- Charging Station Work
Boiler Room/MDP:
- Steel Work
- Roofing
- Cleaning
- Concrete Infills
- Controls Programming
- Mechanical Balancing
Twelve Corners Middle School
Sitework:
- Dumpster Fence & Posts Install
French Road Elementary School
Bus Loop/Parking Lot:
- Signage Installation
Freezer/Cooler Addition:
- Flooring
- Electrical Finishes
- Sump Pump Vent Piping
Dumpster Enclosure:
- Fencing Work
Boiler Room:
- Wall demolition
- Electrical disconnections
Council Rock Primary School
- Abatement Demo - Classrooms 26, 28, and 30
Please note that our schedules are always subject to change based on many factors and opportunities including manpower, material availability, and weather.
Brighton Central School District construction projects will follow the local Town of Brighton Construction Noise Ordinance Hours of 7 a.m. to 7 p.m. Monday through Friday. Please anticipate that there may be varying loud noise between those hours to allow for construction to advance.