2025-26 Construction Schedule

Brighton Construction Schedule

Brighton Construction Schedule for the week of
December 15 to 19, 2025

Below is the anticipated schedule of work from December 15-19, 2025.

Brighton High School

Technology Suite:

  • Flooring installation
  • Lighting installation
  • Mechanical ductwork installation
  • Shelving installation
  • Tech Hallway Ceiling Grid and Lights

Door 20 Addition:

  • Subject to material arriving onsite, the countertop and intercoms for the security office will be installed

Athletic Fields and New Entry Lane:

  • Temporary safety fencing installation
  • Shed demolition pending utility disconnection timelines
  • Subject to material arrival, there will be placement and installation of stone for drop-off loop and temporary laydown area which is next to the Building and Grounds Lot
  • Weather dependent demolition of dugouts, backstop fencing, and scoreboard
  • Weather dependent placement and electrical connections of construction trailers and storage boxes in the Buildings and Grounds lot

Boiler Room:

  • Temporary safety fencing installation outside of the boiler room
  • Mechanical piping disconnections

Twelve Corners Middle School

STEAM Suite:

  • Ceiling and wall painting
  • Millwork installation
  • Flooring installation
  • Mechanical piping
  • Electrical wire pulling

Elevator

  • Electrical card reader installation

French Road Elementary School

Exterior Canopy:

  • Weather dependent, installation of canopy drainage

Please note that our schedules are always subject to change based on many factors and opportunities including manpower, material availability, and weather.

A construction schedule for 2025-26 lists projects for several schools, including Brighton and Twelve Corners.