Construction Schedule

Brighton Construction Schedule

Brighton Construction Schedule for October 26 to November 6, 2026

Below is the anticipated schedule of work from October 26 to November 6.

Brighton High School

Music Suite:

  • Punchlist work consisting of door adjustments, drywall work, lighting controls

Door 20 Addition:

  • Punchlist work consisting of Ceiling Work

Hallways:

  • Painting
  • Flooring Prep
  • Speaker Wiring

Rooms 154/156/Main Lobby/352/354/408

  • Electrical Rough-In
  • Foundation Work
  • Framing

Athletic Fields and New Entry Lane:

  • Soil management plan is set in place. Working with DEC for work approvals.
  • Soil testing around the site for topsoil analysis – following DEC guidelines
  • Excavation
  • Light Pole Base Rough-In
  • Charging Station Work

Boiler Room/MDP:

  • Steel Work
  • Roofing
  • Cleaning
  • Concrete Infills
  • Controls Programming

 

Twelve Corners Middle School

STEAM Suite:

  • Flooring Repairs

Sitework:

  • Dumpster Fence & Posts Install

French Road Elementary School

Bus Loop/Parking Lot:

  • Signage Installation
  • Flag Pole Installation

Freezer/Cooler Addition:

  • Flooring
  • Electrical Finishes

Dumpster Enclosure:

  • Fencing Work
  • Asphalt Paving

Council Rock Primary School

  • Painting - Classrooms 126, 128, 131
  • Final Clean - Classrooms 126, 128, 131
  • Electrical Finishes – Classrooms 126, 128, 131
  • Punchlist 126, 128, 131
  • Furniture Delivery

Please note that our schedules are always subject to change based on many factors and opportunities including manpower, material availability, and weather.

Brighton Central School District construction projects will follow the local Town of Brighton Construction Noise Ordinance Hours of 7 a.m. to 7 p.m. Monday through Friday. Please anticipate that there may be varying loud noise between those hours to allow for construction to advance.