2025-26 Construction Schedule
Brighton Construction Schedule
Brighton Construction Schedule for April 6-17
Below is the anticipated schedule of work from April 6 to 17, 2026.
Brighton High School
Technology Suite:
- Shop equipment connections and adjustments
- Electrical finishes
Door 20 Addition:
- Electrical work
- Hallways and pool area:
- Drinking Fountain replacements
Music Suite:
- Electrical rough-in
- Mechanical rough-in – piping and ductwork
- Framing and drywall
- Panel work
Athletic Fields and New Entry Lane:
- Construction is paused, will continue work once soil management plan is set in place
Boiler Room/MDP:
- Mechanical and plumbing rough-in
- Hot water boiler connections
- Electrical conduit rough-in and panel work
- Plumbing sump pump piping
Twelve Corners Middle School
STEAM Suite:
- Painting
- Electrical work
Stairwells:
- Painting
- Ceiling work
Elevator:
- Electrical card reader programming
- Electrical panel work and testing
French Road Elementary School
Exterior Canopy:
- Roofing drainage work dependent on weather
Main Lobby/Secure Vestibule:
- Metal coiling door electrical connections
- Door hardware
- Painting touch-ups
Freezer/Cooler Addition:
- Excavation
- Foundation work – pile driving
- Stoned laydown area
- Electrical disconnections
- Plumbing drain line work
Council Rock Primary School
Crawlspace:
- Plumbing lines
Please note that our schedules are always subject to change based on many factors and opportunities including manpower, material availability, and weather.
Brighton Central School District construction projects will follow the local Town of Brighton Construction Noise Ordinance Hours of 7 a.m. to 7 p.m. Monday through Friday. Please anticipate that there may be varying loud noise between those hours to allow for construction to advance.