Construction Schedule
Brighton Construction Schedule
Brighton Construction Schedule for October 26 to November 6, 2026
Below is the anticipated schedule of work from October 26 to November 6.
Brighton High School
Music Suite:
- Punchlist work consisting of door adjustments, drywall work, lighting controls
Door 20 Addition:
- Punchlist work consisting of Ceiling Work
Hallways:
- Painting
- Flooring Prep
- Speaker Wiring
Rooms 154/156/Main Lobby/352/354/408
- Electrical Rough-In
- Foundation Work
- Framing
Athletic Fields and New Entry Lane:
- Soil management plan is set in place. Working with DEC for work approvals.
- Soil testing around the site for topsoil analysis – following DEC guidelines
- Excavation
- Light Pole Base Rough-In
- Charging Station Work
Boiler Room/MDP:
- Steel Work
- Roofing
- Cleaning
- Concrete Infills
- Controls Programming
Twelve Corners Middle School
STEAM Suite:
- Flooring Repairs
Sitework:
- Dumpster Fence & Posts Install
French Road Elementary School
Bus Loop/Parking Lot:
- Signage Installation
- Flag Pole Installation
Freezer/Cooler Addition:
- Flooring
- Electrical Finishes
Dumpster Enclosure:
- Fencing Work
- Asphalt Paving
Council Rock Primary School
- Painting - Classrooms 126, 128, 131
- Final Clean - Classrooms 126, 128, 131
- Electrical Finishes – Classrooms 126, 128, 131
- Punchlist 126, 128, 131
- Furniture Delivery
Please note that our schedules are always subject to change based on many factors and opportunities including manpower, material availability, and weather.