2025-26 Construction Schedule
Brighton Construction Schedule
Brighton Construction Schedule for September 14 to 25, 2026
Below is the anticipated schedule of work from September 14 to 25, 2026.
Brighton High School
Technology Suite:
- Painting touch-ups
- Flooring repairs
Door 20 Addition:
- Punchlist work consisting of doors
Hallways:
- Painting
Music Suite & Rooms 226/228/230:
- Electrical Data Cable and Finishes
- Rooms 154/156/352/354/408
- Heat Pump Demo
- Framing
- Electrical Rough-In
- Lighting Installation
- Crawlspace Abatement
Athletic Fields and New Entry Lane:
- Soil management plan is set in place. Working with DEC for work approvals.
- Subbase prep & laying stone
- Asphalt Paving
Boiler Room/MDP:
- Chimney Demolition
- Steel Work
- Roofing
Twelve Corners Middle School
STEAM Suite:
- Flooring repairs
Winton Road Entrance:
- Electrical Rough-In
- Access Controls Installation
Hallways:
- Ceiling Installation
Sitework:
- Concrete Pours
- Dumpster Fence & Posts Install
French Road Elementary School
- Bus Loop/Parking Lot:
- Signage Installation
Freezer/Cooler Addition:
- Concrete Slab Pour
- Asphalt Paving
- Cafeteria:
- Lighting Install
Council Rock Primary School
- Abatement
- Hallway Boarding & Wall Tile
- Bathroom Work
- Painting
- Classroom Plumbing Rough-In
- Electrical Finishes
- Roofing
Please note that our schedules are always subject to change based on many factors and opportunities including manpower, material availability, and weather.
Brighton Central School District construction projects will follow the local Town of Brighton Construction Noise Ordinance Hours of 7 a.m. to 7 p.m. Monday through Friday. Please anticipate that there may be varying loud noise between those hours to allow for construction to advance.