Construction Schedule
Brighton Construction Schedule
Brighton Construction Schedule for Oct. 9 to 16, 2026
Below is the anticipated schedule of work from Oct. 5 to 16, 2026.
Brighton High School
Music Suite:
- Punchlist work consisting of doors, drywall work, lighting controls Door 20 Addition:
- Punchlist work consisting of doors Hallways:
- Painting
Rooms 154/156/352/354/408
-
Heat Pump Demo
-
Electrical Rough-In
-
Foundation Work
-
Mechanical Reheat Coil Work
Athletic Fields and New Entry Lane:
-
Soil management plan is set in place. Working with DEC for work approvals.
-
Excavation
-
Subbase prep & laying stone
-
Asphalt Paving
-
Lighting Rough-In Boiler Room/MDP:
-
Chimney Demolition
-
Steel Work • Roofing
Twelve Corners Middle School
STEAM Suite:
- Flooring Repairs
Winton Road Entrance:
- Ceiling Work Sitework:
- Dumpster Fence & Posts Install
French Road Elementary School
Bus Loop/Parking Lot:
-
Signage Installation
-
Flag Pole Installation
Freezer/Cooler Addition:
-
Lighting Installation
-
Flooring Self Leveler
- Sump Pump Work
Dumpster Enclosure:
-
Fencing Work
-
Asphalt Paving
Council Rock Primary School
-
Painting - Classrooms 126-131
-
Flooring - Classrooms 126-131
-
Millwork - Classrooms 126-131
-
Drywall/Finishing – Classrooms 126-131
-
Electrical Finishes – Classrooms 126-131
-
Punchlist 136 &138
-
Roofing Restoration
- Window Treatments
Please note that our schedules are always subject to change based on many factors and opportunities including manpower, material availability, and weather.
Brighton Central School District construction projects will follow the local Town of Brighton Construction Noise Ordinance Hours of 7 a.m. to 7 p.m. Monday through Friday. Please anticipate that there may be varying loud noise between those hours to allow for construction to advance.