Construction Schedule

Brighton Construction Schedule

Brighton Construction Schedule for Oct. 9 to 16, 2026

Below is the anticipated schedule of work from Oct. 5 to 16, 2026.

 

Brighton High School

Music Suite:

  • Punchlist work consisting of doors, drywall work, lighting controls Door 20 Addition:
  • Punchlist work consisting of doors Hallways:
  • Painting


Rooms 154/156/352/354/408

  • Heat Pump Demo

  • Electrical Rough-In

  • Foundation Work

  • Mechanical Reheat Coil Work

 

Athletic Fields and New Entry Lane:

  • Soil management plan is set in place. Working with DEC for work approvals.

  • Excavation

  • Subbase prep & laying stone

  • Asphalt Paving

  • Lighting Rough-In Boiler Room/MDP:

  • Chimney Demolition

  • Steel Work • Roofing

 

Twelve Corners Middle School

STEAM Suite:

  • Flooring Repairs

Winton Road Entrance:

  • Ceiling Work Sitework:
  • Dumpster Fence & Posts Install

 

French Road Elementary School

Bus Loop/Parking Lot:

  • Signage Installation

  • Flag Pole Installation

Freezer/Cooler Addition:

  • Lighting Installation

  • Flooring Self Leveler

  • Sump Pump Work

Dumpster Enclosure:

  • Fencing Work

  • Asphalt Paving

 

Council Rock Primary School

  • Painting - Classrooms 126-131

  • Flooring - Classrooms 126-131

  • Millwork - Classrooms 126-131

  • Drywall/Finishing – Classrooms 126-131

  • Electrical Finishes – Classrooms 126-131

  • Punchlist 136 &138

  • Roofing Restoration

  • Window Treatments

 

Please note that our schedules are always subject to change based on many factors and opportunities including manpower, material availability, and weather.
 

Brighton Central School District construction projects will follow the local Town of Brighton Construction Noise Ordinance Hours of 7 a.m. to 7 p.m. Monday through Friday. Please anticipate that there may be varying loud noise between those hours to allow for construction to advance.