2025-26 Construction Schedule

Brighton Construction Schedule

Brighton Construction Schedule for September 14 to 25, 2026

Below is the anticipated schedule of work from September 14 to 25, 2026.

Brighton High School

Technology Suite:

  • Painting touch-ups
  • Flooring repairs

Door 20 Addition:

  • Punchlist work consisting of doors

Hallways:

  • Painting

Music Suite & Rooms 226/228/230:

  • Electrical Data Cable and Finishes
  • Rooms 154/156/352/354/408
  • Heat Pump Demo
  • Framing
  • Electrical Rough-In
  • Lighting Installation
  • Crawlspace Abatement

Athletic Fields and New Entry Lane:

  • Soil management plan is set in place. Working with DEC for work approvals.
  • Subbase prep & laying stone
  • Asphalt Paving

Boiler Room/MDP:

  • Chimney Demolition
  • Steel Work
  • Roofing

Twelve Corners Middle School

STEAM Suite:

  • Flooring repairs

Winton Road Entrance:

  • Electrical Rough-In
  • Access Controls Installation

Hallways:

  • Ceiling Installation

Sitework:

  • Concrete Pours
  • Dumpster Fence & Posts Install

 

French Road Elementary School

  • Bus Loop/Parking Lot:
  • Signage Installation

Freezer/Cooler Addition:

  • Concrete Slab Pour
  • Asphalt Paving
  • Cafeteria:
  • Lighting Install

 

Council Rock Primary School

  • Abatement
  • Hallway Boarding & Wall Tile
  • Bathroom Work
  • Painting
  • Classroom Plumbing Rough-In
  • Electrical Finishes
  • Roofing

Please note that our schedules are always subject to change based on many factors and opportunities including manpower, material availability, and weather.

Brighton Central School District construction projects will follow the local Town of Brighton Construction Noise Ordinance Hours of 7 a.m. to 7 p.m. Monday through Friday. Please anticipate that there may be varying loud noise between those hours to allow for construction to advance.